Chapter 10: CCS Project Costs Abstract
This section of the report contains the cost estimate for the End-to-End CCS chain for the purposes of providing potential developers of CCS projects with indicative cost information regarding capital expenditure, operating costs and decommissioning/ abandonment costs.
One of the key objectives of the FEED phase of the UKCCS Demonstration Competition was to increase the cost certainty for the overall project.
During development of the Outline Solution, costs were estimated to an accuracy of -30% to +50%. Through the design and project development across the various Consortium workstreams (as outlined in the previous sections of this report), it has been possible to refine this accuracy and increase the cost certainty of the indicative core capital costs to approximately -12%/+15% accuracy.
The appropriate summary section from the Feed Close Out Report can be downloaded as a PDF below
The main text of the FEED Close Out Report, together with the supporting appendix for this section can be downloaded as PDF files below
FEED Close Out Report
Project Cost