Chapter 1: Programme Abstract
This section of the FEED Close Out Report provides a summary of the programme schedules for the two key phases of the UK CCS Demonstration competition namely:
- The Front End Engineering Design (FEED) phase. This is discussed in Section 1.1.
- The implementation phase of the UKCCS Demonstration Project denoted as the Engineering, Procurement and Construction (EPC) programme. This is discussed in Section 1.2.
The section includes descriptions of execution strategies; risks and critical paths for the programme as well as high level activity descriptions and initial resourcing estimates.
The programmes are loaded as P6 Primavera schedules and managed such that key interface milestones are monitored by the programme managers, with activities updated so as to be able to track progress. Performance metrics were measured and reported on a monthly basis during FEED to manage actual progress against the programme. These programmes are based on assumptions made at the end of Q1 2011.
Programme related support materials for all Consortium Partners and ScottishPower’s selected carbon capture technology provider Aker Clean Carbon are contained within PDFs below.
The appropriate summary section from the Feed Close Out Report can be downloaded as a PDF below
The main text of the FEED Close Out Report, together with the supporting appendix for this section can be downloaded as PDF files below
FEED Close Out Report
FEED Programme
Overall Project Programme